Carson Street Hitting the Home Stretch

2016-10-02_063

October has begun. Fall is in the air, leaves are starting to turn color, and snow has hit the mountain summits. But more importantly to the narrative we’ve been following all summer, this is the month that the Carson Street redevelopment project is going to be finished. I took a walk on Sunday to explore the area. Already we can see some segments that are pretty much finished, as well as other areas that still need some work. The project is scheduled to be done before the Nevada Day parade; let’s see how close they are.

2016-10-02_064

The far south end of the project is the least complete, since they worked from north to south all summer. However, it’s still looking pretty good. At the corner of Fifth and Carson the curbs and sidewalks have been poured, they are just waiting for decorative brick to be laid.

2016-10-02_057

2016-10-02_065

Some of the sidewalks in front of the Legislative Building are still yet to be poured, but this is the only place that sidewalks are still unfinished.

2016-10-02_056

2016-10-02_068

The trees in front of the Legislative Plaza have been saved, which is good to see. New planters have been poured around them.

2016-10-02_070

2016-10-02_073

Unfinished sidewalks are next to large landscaping planters, and areas where brick will go.

2016-10-02_055

Carson Street has been completely repaved now, a big improvement from our last update where there were still piles of dirt here. The final layer of asphalt has only been laid as far south as Proctor Street, though. Here at Fourth there is still a rough intermediate layer in place.

2016-10-02_053

Comma Coffee is taking advantage of the extra sidewalk space for some outdoor dining.

2016-10-02_076

2016-10-02_079

2016-10-02_084

The crosswalk at Third is still being constructed. Concrete and brick have yet to appear on the east side of the street.

2016-10-02_044

On the west side of the street, however, everything is done and looking good.

2016-10-02_045

2016-10-02_046

2016-10-02_051

As shown previously, the sidewalk in front of the St Charles Hotel is raised and styled like wood planks.

2016-10-02_039

On this Sunday a car was taking advantage of one of the new parking spots. Parking on Carson Street, back after 50 years of being forbidden!

2016-10-02_041

The concrete aprons of the parking spots are designed to be distinct from the asphalt of the roadway.

2016-10-02_038

New trees have been planted too. Most of them are in the north half of the project, but one has found its way down this far south.

2016-10-02_088

2016-10-02_090

The crosswalk at Second Street has walls but little else.

2016-10-02_036

On the west side it is more complete.

2016-10-02_093

The stretch of road between Second and Musser is going to be heavily landscaped. Here new grass has been planted in front of the Capitol, creating a large green space on both sides of the road. There is no sidewalk outside of the historic Capitol fence. Pedestrians will have to walk through the Capitol grounds.

2016-10-02_034

Grass has been planted on the west side as well, but here there are sidewalks with wide curved plaza areas. Brick will be going in here as well.

2016-10-02_032

2016-10-02_100

2016-10-02_031

The crosswalk in front of the Capitol still needs some work.

2016-10-02_099

2016-10-02_026

However this stretch of sidewalk is finished and has created a nice park-like atmosphere. This is the only place the sidewalk was kept its previous width, to create as much green space as possible.

2016-10-02_024

2016-10-02_107

2016-10-02_021

Brick was being laid at Carson and Musser.

2016-10-02_016

2016-10-02_111

North of Musser there is less work being done on the sidewalks themselves; they are pretty much finished. That’s not to say there isn’t still work going on. But it is much more detail-oriented.

2016-10-02_113

2016-10-02_013

2016-10-02_010

One of the final details going in is the crosswalks. Every crosswalk through downtown is going to look like this when the project is done. Concrete and brick, inlaid into the asphalt of the street.

2016-10-02_118

The striping has been laid north of Proctor, signaling that the roadbed is finally finished.

2016-10-02_221

One of the new features of the street is dedicated bike lanes.

2016-10-02_220

The parking spot in front of Carson Jewelry and Loan is marked as 5-minute drop-off only. Not sure if that was the city’s idea or the store’s.

2016-10-02_120

The roadbed itself may be done, but work is ongoing on installing the new crosswalks.

2016-10-02_123

They decided it was easier to lay all the asphalt in one continuous pour, then come back later to cut out the sections where the crosswalks are going to go.

2016-10-02_216

All the crosswalks at Telegraph and Carson are done, but some of them are still under protective steel plates.

2016-10-02_209

The bulb-outs at Telegraph are also finished, but still waiting for landscaping.

2016-10-02_127

These crosswalks look pretty fabulous, and will make it more obvious to traffic where there may be pedestrians crossing the street.

2016-10-02_130

This crosswalk in front of Cactus Jack’s was closed off some time ago because it proved to be too dangerous. Now with the narrower street they are reopening it.

2016-10-02_133

2016-10-02_193

This crosswalk at Spear is still being built. The concrete has been poured, now it just needs bricks.

2016-10-02_191

Steel plates on the street protect the newly-built crosswalks from traffic until the concrete has cured and the bricks have gotten a chance to settle in place.

2016-10-02_137

2016-10-02_139

I was disappointed to see that some of the trees north of Robinson had been removed. I thought they would save them and create planters around them like was done in front of the Legislative Building. I guess it was not to be.

2016-10-02_187

New trees are being planted to replace them, however. And some flowers and shrubs are in place in the planters too.

2016-10-02_176

With the sidewalks and roadbed done on this stretch, attention can now be paid to the landscaping.

2016-10-02_180

2016-10-02_185

2016-10-02_183

2016-10-02_141

In places where work has not started on the new crosswalks, their location has at least been marked out. All the asphalt between the pink lines will be removed.

2016-10-02_150

First a concrete frame is poured, then the bricks are laid. Here is another half-finished crosswalk at Ann.

2016-10-02_173

The west side crosswalks are done along this stretch. This week Carson Street is closed so they can install the new crosswalks across Carson.

2016-10-02_172

2016-10-02_170

2016-10-02_151

Landscaping, light poles, flower pots and trash cans. This part of the sidewalk looks like it’s all done. Even the construction cones are gone.

2016-10-02_153

At Sophia the road widens to two lanes again in time to meet up with the untouched road north of William. Even on this part, though, the bike lane remains.

2016-10-02_167

The trees are starting out small but in the coming decades they will grow to provide shade for future generations, and people will wonder why anyone ever spoke out against this project.

2016-10-02_165

New flower pots at Carson and William.

2016-10-02_164

2016-10-02_159

This final crosswalk at William marks the north boundary of the project. On Sunday the asphalt had been marked and cut but was still in place. On Monday I drove by and saw that it had been removed, and they were starting to pour concrete for the crosswalk.

The Nevada Day parade on October 29th has always been the deadline for this project. At first they weren’t sure if all the crosswalks would be done in time, but they are ahead of schedule and feeling more confident. There is still much more work to do, asphalt, concrete, brick and landscaping, but they still have three and a half weeks to get it done. By November 1st we will all be able to enjoy our new downtown. after a decade of anticipation.

Leave a Reply

Your email address will not be published. Required fields are marked *